- Client: Northern Gas Networks
- Value: £120,000
- Duration: 12 weeks
Saltwick offtake was under going a complete site rebuild including pipeline diversions, electrical & instrumentation upgrade and a new flow metering philosophy.
Simkiss were awarded phase 1 of the project, to supply, install and deliver the telemetry kiosk, switchgear kiosk and DNO intake kiosk.
Our strategy was clear from the outset, appointing an approved HIAB contractor to ensure a safe and smooth operation to transport from Manchester to Whitby (Newcastle-Upon-Tyne) on completion
The kiosks consisted of a vast amount of switchgear and control panels which were intricately planned out with attention to detail to ensure they were accessible and aesthetically pleasing on the eye.